Building Construction Week #1 (1/25/2020)
Saturday
Partial framing commences.
Sunday
Partial framing continues. 1 side sheetrock commences. Trench breaking and digging.
Monday
Underground plumbing commences. Sheetrock continues. Partial ceiling paint commences.
Tuesday
Plumbing inspection. Sheetrock continues. Painting continues.
Wednesday
Framing continues. 1 side sheetrock continues. Painting continues. Foundation prep.
Thursday
Framing continues. 1 side sheetrock continues. Painting continues. Foundation inspection.
Friday
Trench cut pour-back. Framing continues. Electrical conduit run commences.