Building Construction Week #3 (2/8/2020)

Saturday

CMU cutouts and lintel installation. Wood beams installation.

Sunday

CMU cutouts and lintel installation. Additional framing.

Monday

Framing continues. Tape/float continues. Electrical work.

Tuesday

Framing and 1 side sheetrock continues. Tape/float continues. Electrical and plumbing work.

Wednesday

Framing and 1 side sheetrock continues. Tape/float continues. Electrical and plumbing work.

Thursday

Framing and 1 side sheetrock continues. Tape/float continues. Electrical and plumbing work.

Friday

Framing and 1 side sheetrock continues. Tape/float continues. Electrical and plumbing work.