Building Construction Week #7 (3/6/20)

Saturday

Door installation.

Sunday

Mirror installation.

Monday

Door installation continues.

Tuesday

Restroom floor tile continues. Electrical work continues.

Wednesday

Electrical work. Restroom floor tile continues.

Thursday

Lights arrive. Electrical and HVAC work continue.

Friday

Electrical and HVAC work continue.

Marlana Doyle