Building Construction Week #5 (2/21/20)

Saturday

Wall cover continues. Tape and float continues. HVAC stud work on ceiling.

Sunday

Low voltage wiring installed.

Monday

Recessed subfloor installation commences. Tape and float.

Tuesday

Recessed subfloor installation continues. Tape and float.

Wednesday

Recessed subfloor installation continues. Tape and float. Painting.

Thursday

Recessed subfloor installation continues. Tape and float. Painting.

Friday

Tape and float. Painting.

Marlana Doyle