Building Construction Week #5 (2/21/20)
Saturday
Wall cover continues. Tape and float continues. HVAC stud work on ceiling.
Sunday
Low voltage wiring installed.
Monday
Recessed subfloor installation commences. Tape and float.
Tuesday
Recessed subfloor installation continues. Tape and float.
Wednesday
Recessed subfloor installation continues. Tape and float. Painting.
Thursday
Recessed subfloor installation continues. Tape and float. Painting.
Friday
Tape and float. Painting.