Building Construction Week #9 (3/20/19)
Saturday
Trash Removal.
Sunday
N/A
Monday
Electrical work. Painting in applicable areas. General cleaning and preparation for subfloors.
Tuesday
Electrical and HVAC work. Painting in applicable areas. Lumber arrives.
Wednesday
Electrical and HVAC work. Painting in applicable areas. Subfloor in C commences.
Thursday
Electrical and HVAC work. Painting in applicable areas. Subfloor in C continues. Roofing work.
Friday
Electrical and HVAC work. Painting in applicable areas. Subfloor in C continues.