Building Construction Week #10 (3/27/20)
Saturday
Subfloor installation commences in A. Electrical and HVAC work.
Sunday
NA
Monday
Subfloor in A continues. Electrical and HVAC work. Painting. Roof penetrations for TPO.
Tuesday
Subfloor in A continues. Electrical and HVAC work. Painting. Roof penetrations for TPO.
Wednesday
HVAC units set on roof. Subfloor in A continues. Electrical and HVAC work. Painting.
Thursday
Roof penetrations for metal roof. Painting. Electrical and HVAC work.
Friday
Restroom partitions measured and ordered. Interior ramps. Painting.