Building Update Week #13 ( 4/14/20)
Saturday
Interior glass installed. Speaker hardware installation.
Sunday
NA
Monday
HVAC and Electrical work. Maple floor drum sanding.
Tuesday
Paint touch-ups and ceiling tiles in restroom. Maple floor sanding completed. Additional speaker hardware installation.
Wednesday
Maple floor wood filler, rotary sanded and buffed. Speaker installation continues.
Thursday
Mezzanine wall sheetrocked. General cleaning and paint touch-ups. Exterior wall painted.
Friday
1st coat sealer on maple floor AM. 2nd coat PM. Restroom partitions installed. Countertops installed. HVAC air balanced.