Building Construction Week #12 (4/10/20)
Saturday
Interior doors and window framing installed. Marley glued down and hot welded.
Sunday
NA
Monday
Electrical and HVAC work.
Tuesday
Maple floor installation commences. Cabinet installation commences.
Wednesday
Front desk delivered. Countertops get measured. Electrical work continues.
Thursday
Electrical work continues. Cabinet hardware installation. Doors and frame paint preparation.
Friday
Electrical and HVAC work. Doors and frames painted.