Building Construction Week #11 (4/3/20)

Saturday

Subfloor commences in B. Harlequin delivery. Acoustic panel delivery.

Sunday

NA

Monday

Subfloor continues in B. HVAC and electrical work continue. Common area floor preparation.

Tuesday

Subfloor continues in B. HVAC and electrical work continue. Common area floor preparation. Ceiling grid in restrooms installed.

Wednesday

Acoustic panel installation. HVAC and electrical work continue. Common area floor preparation.

Thursday

Acoustic panel installation. Electrical work. HVAC start-up. Common area floor preparation.

Friday

Electrical and HVAC work. Plumbing work. Mezz wall framing. Marley rolled out. Common area flooring installation commences. Electrical ceiling cover inspection (Passed)

Marlana Doyle